INTRODUCTION

Project management consist important role in the business to facilitate and organise different aspects in the business. With the help of the proper plan, guidelines implemented in the business so that clear aims and objectives will be set to determine budget as well. It is more important parameter to attain desired results in particular place and implement appropriate functions (Tsaturyan and Müller, 2015). Present report based on the QA higher education to implement new functions and operations in the computing labs in campus areas. In the campus of Birmingham, it helps to provide systematic study program for business development and outcomes as well. In this context, present report covers project initiation document in which budget information defines and framing risk register as well. Furthermore, Work Break Down Structure determines that assists to make effective functioning in the business environment.

TASK 1

Project Initiation document

Initiation Documentation help to create systematic plan in the project that assists to manager to implement diverse range of activities. In this way, appropriate activities frame with involve different aspects in the campus for development of the project. In this regard, it is important to look towards the individual involvement so that budget will be prepare in proper manner (Lee, Reinicke and Anderson, 2015). It helps and support to define proper things and activities in different aspects of QAHE. In this regard, following information required in the project for development of the campus results:

  • Budgetary information: In order to define budgetary information, project consider important role in the business. In this way, estimation helps to implement proper activities to get better work and make systematic results. In respect to implement QAHE there is around £625000 needed for consider different tools such as laptop, computers, manpower, furniture, etc. In this consideration, following aspect develop in the project with budgetary information:

Budget

Total

Tools

Laptop

Computers

Manpower

Furniture

 

Initial amount

10.00%

15.00%

20.00%

30.00%

£625000

Money investment

£62,500.00

£93,750.00

£125,000.00

£187,500.00

£468,750.00

Total requirement

 

 

 

 

£156,250.00

 

  • Time-scale: In this way, it can be stated that there are several numbers of days implemented to finish the whole project. On the basis of time, objectives will be completed to lead with the better functions and operations. The present project started on 1st February 2018 and completed on 19th July 2018. There are total 121 days taken to implement this project.
  • Objectives: Objectives are must important consideration to implement any project. Therefore, it considers tasks and activities which completed on time. Further, blueprint of the project also made in this aspect to get better results at workplace (Pinto, 2014). Main objectives of this project implementation are as follows:
    • To increase students satisfaction level regarding studying.
    • To refurbishment in classroom for increasing knowledge
  • Approaches: In the present project, latest and modify technology requires target more people and better education system as well (Vukomanović, Young and Huynink, 2016). Approaches also helps to facilitate requirement of the student with implement Prince 2 approach.
  • Key staff and stakeholder analysis: Key staff are major consideration that assists to make effective functioning in the environment. In this way, managers of the company need to combine staff and stakeholder to work in the project.

QAHE wants to implement project with refurbishment in class room so that teaching process consider successful results and smooth functioning as well. It helps to gain better associated results. With the help of the Initiation documentation, appropriate date and time consider complete the whole project. Therefore, it is important to look towards the things that are managed properly. Along with this, stakeholder analysis lead to make interpretation that assists to make systematic work performance in the business environment (Martens and Carvalho, 2017).

TASK 2

Risk register

Risk and uncertainty is also important part of each project so that it help to implement activities properly. In this way, needs require understanding properly so that it will concentrate on the major risk which consider proper changes to gain better information and results. In this documentation, all major areas of risk consider solve issues and problems with suitable strategies (Shtub and Rosenwein, 2018). In addition to this, it includes major aspects of the factors to identify QAHE better work and mitigate with the contingency program as well. All these aspects need to implemented by project manager with appropriate tools and techniques to make better work and lead with innovation as well. Risk register need to maintain properly so that activities done in proper manner and manage work as well. In this way, facilities lead to gain better functioning and outcomes in the whole risk management work. Following are different risks elements consider in the project management of QAHE:

Risk name

Likelihood and impact

Score of pre action

Score of post action

Financial risk

This risk could be solve through taking consideration from banking industry. It leads to the better and effective working.

7

5

Resources risk

It impacts on the broad nature that is important to understand. In respect to reduce its impact, it is important to create proper schedule of resources that are used in the whole project

8

5

Technical risk

In this aspect, problem need to implement with solution of technical consideration. QAHE need to make certain changes in the  Birmingham to execute effective operations and functions. In the educational section, it is required proper concentration to work in systematic manner.

8

4

Scope risk

QAHE need to consider some important scope which could be reflect to the positive consideration. It helps to make better and appropriate results in the business environment.

9

6

Legal risk

This risk associated with the regulatory risk option that align with the contract and act with the other sections as well. QAHE need to identify these kinds of risks to try to find ways to deal with factors.

9

5

External hazards

In order to lead with this risk element, QAHE need to concentrate on the time frame through they will consider execution of the project for class room refurbishment towards natural disasters such as earthquakes, etc.

9.5

7

Performance risk

In order to maintain creativity and innovation, QAHE need to concentrate on this element to maintain their quality and performance with minimise performance risk. Institute charges very high fees so that it is important to look towards the same important consideration of the appropriate qualitative tools in the campus.

10

6

Strategic risk

This risk estimated to consider errors in the working. Project management need to concentrate on QAHE education level to implement strategies that enable to deal with the different kinds of hazards. Consideration also needed to make proper working system in the whole project.

8.5

6.2

Governance risk

In respect to follow rules and regulations, governance risk also associated with values, ethics, etc. Therefore, it is important to look towards the better and effective working system in the project management.

10

7

 

Project plan

QAHE need to implement proper plan of Gantt chart and time-scale which helps to consider project in systematic manner. It assists to apply different consideration and overall growth to suitable aspects of the effectiveness and efficiency as well (Bentahar and Cameron, 2015). Task definition also help to develop refurbishment that enable to signify and implement positive aspect in the whole program.

  • Gantt chart: It is the important kinds of project management tool that assists to implement appropriate activities and tasks. In this way, QAHE need to divide whole program in small units and activities so that measurable section could be develop easily.

Task Name

Duration

Start

Finish

Predecessors

Building Management System

112 days

Thu 2/1/18

Fri 7/6/18

 

Initiation phase

15 days

Tue 1/2/18

Mon 1/22/18

 

Setting the target goals of BMS implementation

5 days

Tue 1/2/18

Mon 1/8/18

 

Setting stakeholders expectations

10 days

Tue 1/9/18

Mon 1/22/18

3

Proper and adequate documentations, contracts and agreements

8 days

Tue 1/9/18

Thu 1/18/18

3

Planning phase

21 days

Fri 1/19/18

Fri 2/16/18

 

Setting out operational plans and policies

6 days

Fri 1/19/18

Fri 1/26/18

5

Identifying resource requirement i.e. human source, funds and equipment’s

9 days

Mon 1/29/18

Thu 2/8/18

7

Plan for managing risk

6 days

Fri 2/9/18

Fri 2/16/18

8

Execution phase

21 days

Mon 2/19/18

Mon 3/19/18

 

Collection of funds

5 days

Mon 2/19/18

Fri 2/23/18

9,4

Hiring project team i.e. technical expert, website developer and others

4 days

Mon 2/26/18

Thu 3/1/18

11

Purchase hardware and software license and others

12 days

Fri 3/2/18

Mon 3/19/18

11,12

Testing system functioning

5 days

Fri 3/2/18

Thu 3/8/18

12

Monitoring and controlling phase

91 days

Tue 1/2/18

Tue 5/8/18

 

Continue monitoring of the system functioning and work execution

33 days

Tue 3/20/18

Thu 5/3/18

13

Regular reporting

91 days

Fri 3/2/18

Fri 7/6/18

12

Conducting meetings

5 days

Fri 3/9/18

Thu 3/15/18

14

Analysing the risks

4 days

Fri 5/4/18

Wed 5/9/18

16,14

Examining the progress by comparing the performance with the targets

5 days

Mon 7/9/18

Fri 7/13/18

17

Altering the plan

8 days

Mon 7/9/18

Wed 7/18/18

17,16

Closure phase

1 day

Tue 1/2/18

Tue 1/2/18

 

Contract closure

1 day

Thu 5/10/18

Thu 5/10/18

19

Post-project appraisal and review

1 day

Mon 7/16/18

Mon 7/16/18

20

Submitting the final report to the project manager

1 day

Thu 7/19/18

Thu 7/19/18

21

  • Critical path system: It is another important aspect that assists to consider sequence with network activities to cover the longest duration. It helps to underline operations that are important lead to get completion and enable to better outcomes.

In accordance with the given table, it can be stated that there different milestones that are included which are Initiation phase, Planning phase, Execution phase, Monitoring and controlling phase and Closure phase. All these are effective enough to make sure that the goals and objectives that are set for the project can be attained and that is to develop refurbishment of its teaching rooms and computing labs in the Birmingham Campus. More specifically, at the initial stage the project manager set out the goals so that focus is made deciding on the path through which it can be attained (Harrison and Lock, 2017). Then comes the planning part in which all the requirement like finance, human resource, materials are decided. In execution phase, planning made is executed employees support plays vital role. In monitoring and controlling phrase progress made is analysed and steps are taken overcome the risks. Last stage is closure phase in which final steps of project are taken in which project manager completes all the activities that were set initially. All the steps that were included are important to be covered and when these are completed as per the deadline and budget decided, then it becomes favourable enough to accomplish the project.

TASK 3

Risk management plan

            Project align with the appropriate tools and techniques that assists to accomplish desired results with potential risk. In this aspect, different factors implemented to minimise negative impact. Suitable risk management plan enable to the proper and suitable work system. Quality risk management plan is important to consider rigorous risk management process (Klein, Biesenthal and Dehlin, 2015). QAHE need to understand importance of quality management and complete the project in minimum time period.  There are certain basic elements requires concentrate on the appropriate quality standards plan to make successful project. In this aspect, following are certain major aspects and benefits included to gain and consider efficient risk management plan for refurbishment project:

  • Perfect risk management plan helps to avoid big issues of disaster and beneficial to frame different development activities.
  • It assists to look towards the save revenue and expenses that support to make effective growth and development program as well (Alias, Zawawi and Aris, 2014).
  • Plan also lead to make mental satisfaction to make changes in different things which lead to the successful business operations and take place for right outcomes.
  • It also makes proper judgement to become successful course in future development results.
  • It helps to depict competitive edge so that efficient working system will be develop at workplace.
  • It helps to gain maximum opportunities which deriving to the better outcomes and results in systematic manner in the business environment.

            With the help of proper risk management plan, benefits consider in systematic manner to attain desired results. In this way, it is important to look towards the benefits that helps to solve issues and problems properly. It also supports to project manager to divide activities in different aspects to lead towards IT sections. High standards work performance also develop in this way to facilitate proper functioning and bring positive results as well. Along with this, procedure also need to make changes to lead with the positive and appropriate manner (Cagliano, Grimaldi and Rafele, 2015).

PRINCE 2 methodology

In respect to implement methods, there are different consideration included in project management. These kinds of methodologies helps to make changes in systematic manner. In this aspect QAHE institute need to adopt PRINCE2 that facilitate and make changes in correct aspect. It also helps to focus on the supportive aspect that lead in the following manner:

  • Strength: This technique help to consider appropriate decisions and initialisation. Therefore, it enables to take place in appropriate manner that increase standards. Common language define that help to save time and money in the communication process. All roles and responsibilities define towards each individual towards working (Pollack and Adler, 2015).
  • Limitations: It also considers some limitations regarding roles and responsibilities to choose appropriate methods. Obstacles also manage in systematic manner so that effectiveness will be increasing (Samset and Volden, 2016). In this way, similar culture adopted which evaluate drawback in the methodology.

With the help of different advantages and disadvantages, project manager of QAHE need to implement PRINCE2 in better manner so that best outcomes will be gain in systematic manner. In this way, roles and responsibilities help to perform better work and guide in systematic manner. For instance, PRINCE2 in the chosen institute help to identify project in better manner and fulfil requirement as well. In addition to this, all people also working in systematic manner to gain positive direction as well (Fernandes, Ward and Araújo, 2015). Therefore, each and every person develop their positive direction to deal with the roles and responsibilities. 

CONCLUSION

In order to carry the above report, it can be summarised that project management is important aspect that support to mitigate the risk in different consideration. In this way, suitable outcomes and results ascertain at workplace that requires for gain more systematic information. In this context, report concluded about the project initialisation document that helps to implement proper budget, stakeholder analysis, time-scale, etc. With the help of these kinds of information, successful project develop at workplace of Birmingham. Moreover, it carries risk register that support to solve major issues and challenges that occurs in the business environment and understand better functioning at workplace. Gantt chart has been prepared that help to make innovative results at workplace to evaluate suitable activities in the institute.

REFERENCES

  • Alias, Z., Zawawi, E.M.A. and Aris, N.M., 2014. Determining critical success factors of project management practice: A conceptual framework. Procedia-Social and Behavioral Sciences, 153, pp.61-69.
  • Bentahar, O. and Cameron, R., 2015. Design and Implementation of a Mixed Method Research Study in Project Management. Electronic Journal of Business Research Methods, 13(1).
  • Cagliano, A.C., Grimaldi, S. and Rafele, C., 2015. Choosing project risk management techniques. A theoretical framework. Journal of Risk Research, 18(2), pp.232-248.
  • Fernandes, G., Ward, S. and Araújo, M., 2015. Improving and embedding project management practice in organisations—A qualitative study. International Journal of Project Management, 33(5), pp.1052-1067.
  • Harrison, F. and Lock, D., 2017. Advanced project management: a structured approach. Routledge.
  • Klein, L., Biesenthal, C. and Dehlin, E., 2015. Improvisation in project management: A praxeology. International journal of project management, 33(2), pp.267-277.
  • Lee, L., Reinicke, B. and Anderson, R., 2015. Learning through interactions: improving project management through communities of practice. Project Management Journal, 46(1), pp.40-52.
  • Martens, M.L. and Carvalho, M.M., 2017. Key factors of sustainability in project management context: A survey exploring the project managers' perspective. International Journal of Project Management, 35(6), pp.1084-1102.
  • Pinto, J.K., 2014. Project management, governance, and the normalization of deviance. International Journal of Project Management, 32(3), pp.376-387.
  • Pollack, J. and Adler, D., 2015. Emergent trends and passing fads in project management research: A scientometric analysis of changes in the field. International Journal of Project Management, 33(1), pp.236-248.
  • Samset, K. and Volden, G.H., 2016. Front-end definition of projects: Ten paradoxes and some reflections regarding project management and project governance. International Journal of Project Management, 34(2), pp.297-313.
  • Shtub, A. and Rosenwein, M., 2018. Hands-on Project Management: Practice your Skills with Simulation Based Training. World Scientific Books.
  • Tsaturyan, T. and Müller, R., 2015. Integration and governance of multiple project management offices (PMOs) at large organizations. International Journal of Project Management, 33(5), pp.1098-1110.
  • Vukomanović, M., Young, M. and Huynink, S., 2016. IPMA ICB 4.0—A global standard for project, programme and portfolio management competences. International Journal of Project Management, 34(8), pp.1703-1705.

FREE Features

  • Topic Creation
    £ 11 FREE
  • Outline
    £ 14 FREE
  • Unlimited Revisions
    £ 31 FREE
  • Editing/Proofreading
    £ 42 FREE
  • Formatting
    £ 12 FREE
  • Bibliography
    £ 11 FREE

Get all these features for

£ 121FREE